Garage

IMG_1414

IMG_1382

IMG_1332

IMG_1349

IMG_1317

IMG_1314

IMG_1305

IMG_1302

IMG_6340

Now that the old cottages have been demolished we can start on the garage. It is a double garage with carport with a very useful loftspace, situated on the site of the old dwellings. Timber frame construction, with a block and beam floor.

25 March – The Big Day!

hIMG_1192

IMG_1167

In 50 minutes the houses are down.

IMG_1155

IMG_1164

IMG_1142

IMG_1144

Demolition of the houses begins

IMG_1134

We are required to employ an Ecologist with a Bat license to oversee the removal of the roof tiles in case the Bat which was in the loft at some time is found. The Ecologist arrives and the tile removal is underway. By 2pm the tiles are all removed along with the roof trusses. As I expected no Bats were found!

IMG_1112

Finally we are in a position to demolish the cottages. The plant arrives at 7:30.

18 March – Windows arrive

The windows were purchased supply and fit. The crew supplied by the window manufacturer prove to be quite unhelpful. As soon as they arrive on site (one and a half hours late) they look for reasons not to fit the windows and several of those that they do fit they damage while fitting. They leave site having only fitted 12 out of the 29 windows and inform us that they dont know when they will return to complete the job.  Potton were on to it immediately and ask the manufacturer not to send  the fitters back, and they arrange for the team erecting the timber frame to complete the job.

IMG_1107

IMG_1099

The windows arrive on site. They are glazed and finished all ready for installation.

Roof Trusses

14 March. After only 42 days  the house is now really taking shape.

IMG_1090

IMG_1098

IMG_1087

Looking at the cavernous space up here we make a snap decision to get some drawings done to add a staircase to the loft area. It involves a slight reconfiguration to the first floor but gives us an additional 340 sq ft of space. Otherwise, with the planned loft ladder we would only make one visit a year up here to get the Christmas tree! Sorry make that two visits – I would have to take it back!

IMG_1053

The snow starts and is blowing horizontally but we keep going.

IMG_1037

The first truss goes up. It is bitterly cold this morning with a real feel temperature of -10ºC and it REALLY FEELS like it!

IMG_1017

We have a platform system erected on the first floor, making it easy for the guys to walk about and install the roof trusses.

IMG_1084

The crane is a monster and makes easy work of the job in hand

IMG_1005

The first load of two arrives.

IMG_0954

11 March and the 29 Ton crane arrives to offload the Roof Trusses and lift them up onto the building.

IMG_0940

Erecting the timber frame.

With the timber onsite the carpenters started work. First job was to batten the whole base. This was then checked for levels and we found that it was only 10mm out at the worst point. Pretty impressive, but this was made perfectly level using small plastic wedges.

9Z2W2152